Agile teams on the public works work-order ART expect the RTE to estimate their stories during PI Planning. How should the RTE respond?
Select an answer to reveal the explanation.
Short Explanation
The people who do the work-order work own the numbers. The RTE sets the room up and keeps the clock; the RTE does not guess story points for the teams. Honest plans come from the teams who will do the work.
Full Explanation
SAFe keeps estimation and team planning with the Agile teams who will do the work. The RTE facilitates PI Planning, dependency discussion, and risk ROAM; the RTE does not substitute as estimator-in-chief. Business Owner points are business value, not story size. Promoting stories to features to change who estimates avoids the real accountability.