Facilities booked only a single auditorium and forgot breakout rooms and visualization boards for on-site PI Planning of the public works work-order ART. What readiness issue should the RTE raise?
Select an answer to reveal the explanation.
Short Explanation
A PI Planning room is not a TED talk. Public-works crews need side rooms and boards the way a field shop needs bays, not just a podium. If facilities only reserved a lecture hall, logistics readiness is broken and the RTE should fix space and visualization before the event.
Full Explanation
PI Planning preparation includes logistics readiness: sufficient space, breakout rooms, and visualization surfaces so teams can draft plans and make dependencies visible. A single auditorium supports presentations but not team breakouts or a program board. Content and training readiness are separate checks and are not implied by a missing room layout.