Two weeks before PI Planning, Business Owners for the public-health immunization registry ART have skipped briefing prep and left capacity and value questions unanswered. What should the RTE do?
Select an answer to reveal the explanation.
Short Explanation
PI Planning without prepared Business Owners is like opening an immunization clinic with the vaccine fridge unchecked. The RTE does not pray the day goes well; they escalate early with a specific ask so people can still show up ready.
Full Explanation
Effective RTEs treat PI Planning readiness as an ART-level risk, not a last-minute hope. Business Owners assign business value, participate in the briefing, and help resolve issues during planning; unprepared owners weaken objectives and the confidence vote. A timely, specific readiness ask is servant leadership, not blame. Waiting until the event, canceling wholesale, or dumping the gap on Scrum Masters leaves the train without the decision makers it needs.