During an unusual plant recovery operation, management asks whether a Planned Special Exposure (PSE) under NRC 10 CFR 20.1206 can be authorized so a skilled mechanic can exceed the routine 5 rem annual occupational TEDE limit when extra qualified staff are available. Under 10 CFR 20.1206, when is a PSE legally permitted?
Select an answer to reveal the explanation.
Short Explanation
Think of a Planned Special Exposure as an emergency fire-escape hatch, not a fast-pass lane for outage scheduling. You can only use a PSE when no practical alternative exists to avoid the higher dose, so having extra qualified workers available disqualifies it. The classic trap is assuming worker consent or local sign-off alone overrides routine annual limits.
Full Explanation
Under NRC 10 CFR 20.1206, a Planned Special Exposure is permitted Only in an exceptional situation when alternatives that avoid the higher exposure are unavailable or impractical, making that strict condition the only valid basis here. Because extra qualified mechanics are available to share the task within routine 10 CFR 20.1201 limits, management cannot authorize a PSE. Whenever the worker signs a voluntary consent waiver before entering the area fails because worker notification and informed consent are necessary conditions, not standalone justifications; a worker cannot simply waive federal dose limits. When routine outage schedules require overtime in elevated radiation fields fails because normal maintenance and schedule pressure do not qualify as exceptional situations. Whenever the Radiation Safety Officer approves an internal administrative extension fails because internal RSO sign-off cannot bypass 10 CFR 20.1206 criteria or eliminate prior written authorization from senior management. As a regulatory caveat, even a valid PSE is capped at one times the annual 10 CFR 20.1201 limit in a single year and five times that limit over a lifetime, and it must be tracked separately from routine dose. Operationally, confirm whether crew rotation, remote tooling, or temporary shielding can keep all workers under routine limits before initiating a PSE package.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.