Quiz 7 Question 17 of 20

At a pre-install huddle for a 150-kW ground-mount site, the crew lead points to a circle on the array plan marked '3 / S-501' with an arrow at a pier. The drawing index splits sheets into E-series and S-series, and the general notes require embeds to be verified before concrete. Which sheet should the crew lead open to see the pier's anchor bolts and rebar?

Select an answer to reveal the explanation.