Quiz 7 Question 3 of 20

A specialty chemical plant certified to ISO 14001 outsources its bulk tank-cleaning and drum-crushing operations to an on-site contractor. How must the facility address these contracted activities within its environmental management system?

Select an answer to reveal the explanation.