Quiz 5 Question 17 of 20

A chemical plant is preparing to conduct an initial Process Hazard Analysis for a new reactor system that will hold chlorine above the OSHA Process Safety Management threshold quantity. Under 29 CFR 1910.119, what must the facility compile before the Process Hazard Analysis team begins its review?

Select an answer to reveal the explanation.