An environmental engineering firm is mobilizing crews to excavate petroleum- and solvent-contaminated soil at an inactive manufacturing site governed by OSHA HAZWOPER (29 CFR 1910.120). Before field personnel enter the exclusion zone, what document must the project team establish to specify site-specific hazards, PPE levels, air monitoring, and emergency procedures?
Select an answer to reveal the explanation.
Short Explanation
Sending a remediation crew into contaminated soil with only a generic safety manual is like sailing without a chart of the local rocks. Under OSHA 29 CFR 1910.120, you must establish a written site-specific health and safety plan before site entry begins. Avoid the trap of substituting shipping paperwork or community inventory filings for operational field safety controls.
Full Explanation
OSHA 29 CFR 1910.120 requires employers at uncontrolled hazardous waste operations to develop and implement a written site-specific safety and health plan covering each phase of site operations. Selecting A written site-specific health and safety plan tailored to site hazards is correct because it defines task-specific risk analyses, PPE selection, medical surveillance, air monitoring protocols, decontamination, and emergency response before workers enter hazard zones. Choosing A generic corporate injury and illness prevention policy fails because general company policies lack site-specific chemical contaminants, exclusion zone boundaries, and real-time action levels. Choosing A Uniform Hazardous Waste Manifest signed by the site owner fails because manifests track off-site hazardous waste transportation under RCRA rather than protecting on-site excavation workers. Choosing A Tier II hazardous chemical inventory report for local fire crews fails because EPCRA Section 312 reporting informs local planners of routine facility storage rather than governing active remediation work. As a caveat, the plan must be kept on site and updated whenever new contaminants or unexpected site conditions are encountered. As an operational check, conduct a pre-entry tailgate briefing using the plan, verify worker sign-offs, and confirm emergency hospital routes and communication channels.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.