A remediation crew is excavating drums containing unknown organic liquids at an uncontrolled hazardous waste site under OSHA HAZWOPER. Before entry begins, the site safety officer establishes three distinct work zones to prevent cross-contamination. Where should the decontamination corridor be positioned?
Select an answer to reveal the explanation.
Short Explanation
Picture a mudroom between a muddy backyard and a clean living room—you take your boots off in the buffer space, not on the sofa or in the garden. Under OSHA HAZWOPER site control, decontamination belongs in the Contamination Reduction Zone so contaminants never reach clean areas. Watch out for the trap of placing decon right at the excavation face, where workers and wash water would immediately be re-contaminated.
Full Explanation
Under OSHA 29 CFR 1910.120, hazardous waste sites are divided into three zones to control the spread of contamination: the Exclusion Zone, the Contamination Reduction Zone, and the Support Zone. Positioning the decontamination corridor Within the Contamination Reduction Zone between the hot line and the support area creates a dedicated buffer where workers remove PPE and wash off residues before entering clean areas. Placing decontamination Inside the Exclusion Zone immediately adjacent to the active drum excavation pit fails because airborne vapors and splashes from active work would re-contaminate personnel and rinse water. Locating it Inside the Support Zone near the clean command post and equipment staging trailer defeats site control by tracking hazardous residues into the uncontaminated administrative area. Setting up Along the outer perimeter fence outside all controlled site access checkpoints leaves workers walking through clean zones while still contaminated. A key caveat is that the decontamination corridor layout must account for prevailing wind direction so vapors blow toward the hot zone rather than the support area. As an operational check, inspect the hot line boundary and verify that all personnel and equipment exit exclusively through the decontamination corridor.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.