A manufacturing plant operating as a RCRA Large Quantity Generator prepares its first off-site shipment of drummed D001 ignitable solvent waste to a permitted treatment facility. In addition to the Uniform Hazardous Waste Manifest, what must accompany this initial shipment under Land Disposal Restrictions rules?
Select an answer to reveal the explanation.
Short Explanation
Sending hazardous waste off site takes more than a manifest when it is headed for treatment and disposal. Your trap is assuming air, inventory, or new-chemical forms travel with the drum, when RCRA requires a specific notice telling the facility what treatment standards apply.
Full Explanation
Under RCRA 40 CFR 268.7, a generator shipping restricted hazardous waste off site for the first time must send a written Land Disposal Restrictions notice with waste codes and standards to the receiving treatment, storage, or disposal facility. This notice informs the receiving facility of applicable EPA hazardous waste codes, treatability group, and treatment standards so the waste is properly treated before land disposal. A signed TSCA Premanufacture Notice exemption certificate for the spent solvent applies to new chemical manufacturing exemptions rather than hazardous waste disposal shipments. A complete EPCRA Section 313 Toxics Release Inventory chemical calculation worksheet is used for annual community right-to-know reporting and does not accompany waste shipments. An approved Clean Air Act Title V operating permit modification application governs stationary air emission sources rather than drummed waste transfers. As a caveat, generators must retain a copy of the LDR notification and send a new notice if the waste composition or receiving facility changes. As an operational check, verify that the manifest waste codes match the LDR notice and confirm receipt with the receiving facility before subsequent shipments.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.