A robotics lab runs an isolated prototype with no production data, no path to the factory network, and a written risk appetite that allows this class of lab system. A reviewer asks what the design decision should be. Which decision matches the appetite?
Select an answer to reveal the explanation.
Short Explanation
When the fence already matches the rule you wrote down, you record the decision and you pick a day to look again. You do not drop a data-center firewall in front of an isolated bench, mislabel the bench as production, or buy a policy and throw away the record.
Full Explanation
Risk work is not a demand to add controls after the remaining risk is already inside the stated appetite. This prototype is isolated and holds no production data, and the appetite names that class as acceptable. The matching decision is a written acceptance with an owner and a review date, so the exception cannot become permanent by silence. Extra production controls and a false high-impact label spend effort the appetite did not ask for. Record risk acceptance for the prototype and set a date to review it is the design that meets this requirement. Insert a data-center firewall pair in front of a system that has no production path is the wrong fit because a data-center firewall pair does not change a risk the appetite already allows on an isolated lab system. Classify the prototype as a high-impact production system and apply that full baseline is the wrong fit because calling it high-impact production contradicts the scope: no production data and no factory path. Transfer the risk with an insurance policy and skip any record of the acceptance is the wrong fit because insurance is not a record of who accepted the residual risk or when it must be reviewed. Exam caveat: Acceptance expires. If someone later connects the prototype to the factory network, the recorded scope is no longer true and the decision has to be remade. Operational check: Read the acceptance entry and confirm it names the prototype, the owner, the isolation assumption, and a review date on the calendar.