A school district is improving the laptop health signals it collects, including encryption and patch state, before a device may open a SaaS application. On the CISA Zero Trust Maturity Model, which placement of that work is correct?
Select an answer to reveal the explanation.
Short Explanation
You judge a fleet by the condition of the trucks, not by the cargo they might haul later. Laptop health signals collected before SaaS access belong on the Devices pillar. You would misfile that work on the Data pillar, or call the district Optimal, off one new signal.
Full Explanation
The CISA Zero Trust Maturity Model v2.0 uses pillars so endpoint work is not filed as data work, and it uses stages separately from those pillars. Laptop health signals such as encryption and patch state, collected before SaaS access, describe the device. Placing the laptop health signals on the Devices pillar is the correct placement, because that pillar covers the condition of the endpoint before access is allowed. Recording the laptop-health effort on the Data pillar because the laptops will later open school data files the work under data even though the signals describe the endpoint. Marking the district at the Optimal stage because a pilot collects one new health signal confuses a maturity stage with a pillar, and a stage label does not answer where this work sits. Classifying the effort as a Networks pillar project because the laptops join school Wi-Fi talks about the network path, while the signals in the question are device health. On the exam, device health belongs on the Devices pillar, the data itself belongs on the Data pillar, and Optimal is a stage rather than a pillar. In operations, list the signals in this project, confirm they are endpoint conditions such as encryption and patch state, and file the work on the Devices pillar.