When closing out a multi-year commercial construction project trailer, a foreman asks whether the past two years of completed OSHA Form 300 logs, 300A summaries, and 301 reports can be shredded. What must the site supervisor instruct?
Select an answer to reveal the explanation.
Short Explanation
Closing out a job trailer feels like a fresh start, so you might be tempted to toss old safety binders in the shredder. The trap is thinking recordkeeping ends when the project wraps up or that only the annual summary matters. Keep the OSHA 300 logs, 300A summaries, and 301 reports for five full years after the calendar year they cover.
Full Explanation
Under 29 CFR 1904.33, employers must save the OSHA 300 Log, the privacy case list if one exists, the annual summary (Form 300A), and the OSHA 301 Incident Report forms for five years following the end of the calendar year that these records cover. Therefore, the supervisor must "Retain the OSHA 300, 300A, and 301 records for five years after the year they cover" by transferring them securely to the company office when the trailer closes. Choosing to "Shred the individual 301 incident reports immediately while keeping only the 300A summary" violates the retention rule because all three recordkeeping forms must be preserved together for the full five-year period. Choosing to "Discard all safety recordkeeping binders once the building receives its occupancy permit" improperly ties federal record retention to project completion rather than the statutory calendar-year timeline. Choosing to "Destroy the logs after two years if the company had no fatalities during the project" applies a nonexistent exception, as the five-year retention requirement applies regardless of injury severity. As a caveat, during that five-year retention period, employers must also update the stored OSHA 300 Log if newly discovered recordable cases or outcome changes occur. For an operational check, log all archived project safety binders in the main office document register with their calendar-year retention dates before clearing any jobsite trailer.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.