Quiz 14 Question 16 of 20

After installing perimeter guardrails and debris netting on a multi-story concrete frame, a safety technician updates the project risk register and notices that wind-blown hand tools still pose a moderate hazard. How should the technician address this residual risk?

Select an answer to reveal the explanation.