Quiz 3 Question 4 of 20

A mechanical crew plans to arc-weld pipe hangers on an elevated mezzanine while cardboard shipping boxes and wood pallets sit twenty feet away on the same deck. What fire prevention measure must the safety technician require before welding begins?