Quiz 13 Question 17 of 20

A chemical plant operating an OSHA Process Safety Management (PSM)-covered ammonia system schedules regular thickness testing on pressure vessels and function checks on emergency relief valves. Which PSM element requires these ongoing inspection and testing procedures to prevent catastrophic releases?

Select an answer to reveal the explanation.