Quiz 4 Question 3 of 20

During a one-day process audit of a pharmaceutical packaging line, an auditor checks five batch records and finds that all five lack required line-clearance verification signatures. Four other departments remain on the schedule before the closing meeting. What should the auditor do next?

Select an answer to reveal the explanation.