Quiz 1 Question 1 of 20

Following an internal audit finding on solder-paste thickness defects, the production manager submits a corrective action response stating that all affected boards were reworked and the stencil was cleaned. What should the auditor do before accepting this response?

Select an answer to reveal the explanation.