An evaluation committee completes scoring for a city's 4-million-dollar enterprise permitting software Request for Proposals and selects the top-ranked proposer. Before the city manager signs the final contract, what procedural step should the buyer take?
Select an answer to reveal the explanation.
Short Explanation
Rushing straight from evaluation scoring to a signed contract is like skipping the inspection before closing on a house. You need to issue a written notice of intent to award and wait until any protest period the city's code requires has closed so any losing proposer has a fair chance to raise concerns before work starts. The trap is letting the winner start early, which creates costly legal exposure if a protest succeeds.
Full Explanation
Transparency and procedural fairness at the conclusion of a competitive RFP protect both the agency and the vendor community. Choosing to Issue a written notice of intent to award to all proposers and do not execute the contract until any protest period the city's code requires has closed notifies every offeror of the recommended selection and preserves the right to debriefing or timely protest before binding obligations begin. Under the ABA Model Procurement Code a timely protest stays the procurement, which is not one nationwide pre-signature standstill, so the window is what the city's code requires. Choosing to Authorize the selected vendor to begin software configuration immediately under a verbal letter of intent creates an unauthorized commitment and termination exposure if a protest is sustained. Choosing to Keep the winning proposal and the composite score sheet, and archive individual scorecards only through the protest period in the city code violates retention rules because the complete file with all proposals and scoring records must be kept beyond the protest window. Choosing to Contact the runner-up proposer privately to ask whether it can match the top-ranked vendor's pricing is improper price auctioning that violates fair competition. Log the notice posting time and hold any signature or purchase order until any required protest period closes.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.