A county fleet manager wants the buyer to award an Invitation for Bids for utility vehicles based on estimated five-year fuel and maintenance expenses rather than purchase price alone, even though the published solicitation only requested unit prices. How should the buyer proceed?
Select an answer to reveal the explanation.
Short Explanation
You cannot change the rules of the race after the runners have already crossed the finish line. The trap is letting a well-meaning fleet manager inject unpublished life-cycle estimates after bid opening, which destroys transparency and invites an immediate bid protest.
Full Explanation
To preserve fair and open competition under sealed bidding, the buyer must Award on the published price basis or cancel and re-solicit with LCC terms. Under an Invitation for Bids, award criteria must be objective and fully disclosed in the solicitation so every bidder competes on identical terms; life-cycle costing is valid only when the exact formula, discount rate, and cost factors are stated upfront. Choosing to Award using estimated fuel costs calculated privately by the fleet manager applies unstated evaluation criteria and exposes the county to successful protest. Trying to Ask the lowest bidder after bid opening to submit five-year maintenance guarantees constitutes improper post-bid negotiation that alters material terms. Attempting to Switch the solicitation to a negotiated Request for Proposals after opening violates statutory sealed-bid procedures once prices are publicly exposed. As a caveat, canceling and re-soliciting is justified when awarding on purchase price alone would clearly fail to meet the agency's fiscal interest. For an operational check, confirm that any future life-cycle solicitation includes the calculation worksheet and verifiable data sources in the bid package.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.