Quiz 13 Question 4 of 20

One year into a municipal park-mowing contract, the city's facilities director asks the buyer to issue a change order adding full janitorial and HVAC maintenance for three downtown office buildings to the same contract. Which compliance principle should guide the buyer's response?

Select an answer to reveal the explanation.