Quiz 12 Question 11 of 20

During an active Invitation for Bids for municipal storm-sewer repairs, a project engineer accidentally emails the agency's confidential independent cost estimate to one prospective bidder. What must the buyer do to maintain regulatory compliance and fair competition?

Select an answer to reveal the explanation.