Quiz 4 Question 6 of 20

During a municipal water-plant upgrade, the utility engineer needs to shift the location of an interior control panel by ten feet—work clearly within the contract's general scope—and the contractor delays signing a price proposal while critical piping waits. Under a standard public-works Changes clause, what action keeps the project moving?

Select an answer to reveal the explanation.