During a municipal water-plant upgrade, the utility engineer needs to shift the location of an interior control panel by ten feet—work clearly within the contract's general scope—and the contractor delays signing a price proposal while critical piping waits. Under a standard public-works Changes clause, what action keeps the project moving?
Select an answer to reveal the explanation.
Short Explanation
Public-works projects cannot sit idle every time a minor in-scope adjustment waits on final pricing paperwork. Your trap is either letting field staff issue informal verbal orders or escalating straight to termination. When a change falls within the contract's general scope, a unilateral written change order keeps construction moving while preserving equitable pricing.
Full Explanation
The proper contract administration step is to "Issue a unilateral written change order and settle pricing later" because a standard Changes clause empowers the contracting authority to direct in-scope work in writing without halting the schedule for prior price agreement. The contractor remains entitled to seek an equitable adjustment in price or time through the contract's formal valuation procedures. Choosing to "Allow a field inspector to authorize the relocation verbally on site" creates an unauthorized commitment and leaves scope, cost, and warranty responsibility undocumented. Deciding to "Terminate the contract for default immediately over the pricing delay" is disproportionate and skips required cure procedures when the contractor has not abandoned the work. Attempting to "Open a separate competitive solicitation just to move the panel" is impractical on an active construction site, creates warranty conflicts between contractors, and causes needless schedule delays. Caveat: confirm that the relocation truly remains within the general scope of the original contract. A cardinal change is outside the general scope, is not a proper change order even if both parties agree, and needs a new competition. As an operational check, log the written change directive with a not-to-exceed estimate and track the contractor's cost proposal deadline.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.