Four months into a state university's ERP implementation contract, the consulting firm notifies the contract administrator that its designated lead architect is moving to another project and will be replaced immediately by a junior analyst. The executed contract names the lead architect as key personnel. What should the contract administrator do first?
Select an answer to reveal the explanation.
Short Explanation
Swapping a named expert for a rookie mid-project is like hiring a master carpenter and getting an apprentice on framing day. You should enforce the key-personnel clause requiring prior written approval of an equally qualified replacement, avoiding the trap of rubber-stamping a downgrade just to keep the calendar moving.
Full Explanation
Key-personnel provisions protect the agency's evaluation bargain when specialized expertise drove the original award. Choosing to enforce the key-personnel clause requiring prior written approval of an equally qualified replacement preserves technical quality by requiring the vendor to submit resumes, verify comparable credentials, and obtain formal consent before any transition occurs. Deciding to issue a cure notice terminating the contract for default unless the original architect returns demands an unreasonable cure by insisting on the same person rather than an equally qualified substitute and leaps toward termination before qualifications are assessed. Choosing to accept the junior analyst on a trial basis and review performance after thirty days waives prior-approval protection and allows potentially unqualified work to proceed, inviting rework and later schedule slippage. Deciding to negotiate a lower hourly billing rate for the junior analyst through a bilateral modification adjusts pricing without restoring the missing technical capability the university evaluated and paid for. Keep in mind that if the vendor cannot supply an equivalent candidate, the administrator must escalate through formal cure procedures. As an operational check, compare the proposed replacement's qualifications against the original proposal scoring criteria and record written approval in the contract file.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.