Four months after a municipal transit authority inspects, accepts, and pays for twenty solar bus-shelter lighting units, six units fail due to an internal controller manufacturing defect. Which contract administration action should the buyer take first?
Select an answer to reveal the explanation.
Short Explanation
Once you sign off on a delivery, the receiving dock chapter closes, but the warranty chapter is just getting started. When a hidden manufacturing defect surfaces months later, your first move is to put the contractor on formal written notice under the warranty clause to fix or replace the faulty units. Avoid the trap of hiring a third party right away or trying to rewrite old receiving paperwork, which can forfeit your contractual remedies.
Full Explanation
Notify the contractor in writing under the warranty clause to repair or replace the defective units at no cost is the right first step because formal acceptance transfers ownership and triggers post-acceptance warranty protections for latent defects. Written notice preserves the agency's legal rights and gives the contractor the required opportunity to cure at its own expense. Issue a deductive contract modification to recover the original purchase price of all twenty lighting units from the supplier fails because a deductive modification cannot unilaterally claw back full payment for functioning units before allowing warranty remediation. Solicit emergency quotes from a local electrical contractor and deduct the repair invoice from unrelated vendor payments fails because bypassing warranty notice can void coverage, and offsetting unrelated contracts without legal authority creates dispute risk. Reopen the receiving report and retroactively reject the entire shipment because the units failed within six months also fails because receiving rejection applies at inspection before acceptance, whereas post-acceptance failures are governed by warranty terms. As a caveat, verify the exact warranty start date, coverage exclusions, and notice deadline in the executed contract before sending the demand. As an operational check, log the failure dates, serial numbers, and written warranty notice in the contract file and calendar a follow-up deadline to verify completed repairs.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.