Quiz 3 Question 15 of 20

Four months after a municipal transit authority inspects, accepts, and pays for twenty solar bus-shelter lighting units, six units fail due to an internal controller manufacturing defect. Which contract administration action should the buyer take first?

Select an answer to reveal the explanation.