A state university's campus roofing contractor ignored a formal ten-day cure notice after abandoning work mid-project, leaving buildings exposed to rain. The university must hire a replacement contractor immediately at a higher price. Which contract remedy should the contract administrator execute?
Select an answer to reveal the explanation.
Short Explanation
When a contractor walks off the job and ignores a cure notice, your roof is literally on the line. The trap is using a convenience termination that lets the defaulting vendor off the hook. By terminating for default, you protect the university's right to re-procure the work and pursue the excess cost.
Full Explanation
Because the contractor committed an unexcused material breach and failed to respond within the cure period, the university should Terminate for default and document excess reprocurement costs for recovery from the vendor. Default termination ends the breaching vendor's right to proceed, triggers any performance bond protections, and preserves the agency's legal claim for the price difference charged by a replacement contractor. Choosing to Terminate the contract for convenience and pay full lost-profit claims rewards a nonperforming contractor and surrenders the agency's right to recover excess completion costs. Choosing to Assess liquidated damages and direct the same contractor to resume under a bilateral schedule extension treats abandonment as a minor delay and depends on cooperation from a vendor that already ignored formal notice, which cannot protect exposed buildings. Choosing to Issue a bilateral modification deleting the unfinished roofing work and releasing the contractor from further obligations requires mutual agreement and inappropriately waives the contractor's breach. Caveat: always coordinate default terminations with legal counsel and the surety, if bonded, so notice requirements are strictly satisfied. Operational check: compile dated inspection photos, the unanswered cure notice, and competitive reprocurement quotes in the contract file before issuing the formal termination notice.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.