A county's road-striping contractor finishes 20 days past the contractual completion date without an approved excusable delay, causing measurable traffic-control expenses. The executed contract includes a pre-established daily liquidated damages clause. Which action should the contract administrator take?
Select an answer to reveal the explanation.
Short Explanation
Crossing the finish line late still costs your agency real money, even when the final paint looks great. You should enforce the agreed liquidated damages rate against the final invoice, avoiding the trap of waiving valid remedies, double-charging costs on top of that rate, or holding payment for a schedule that is now moot.
Full Explanation
Because the contract already specifies a pre-agreed remedy for unexcused schedule overruns, the administrator should Assess the documented liquidated damages against the contractor's final payment. Liquidated damages are designed to reasonably estimate hard-to-quantify public delay costs and compensate the agency without requiring prolonged litigation over exact damages. Choosing to Waive the delay altogether because the striping work was eventually completed satisfactorily surrenders an enforceable taxpayer remedy and sets a precedent that undermines schedule accountability. Deciding to Bill the contractor for the measured traffic-control invoices in addition to the daily liquidated-damages rate improperly double-counts delay costs, because the daily rate is already the exclusive agreed compensation for late completion and cannot be stacked with actuals. Deciding to Withhold the final payment until the contractor submits a recovery schedule for work that is already finished misuses a forward-looking management tool that is moot once performance is complete and provides no legal basis to delay earned payment. As a caveat, verify that no agency-caused delays or pending time-extension requests offset those 20 days before deducting funds. For an operational check, attach the daily delay calculation and written notice of assessment to the final invoice package before releasing payment.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.