Midway through a county library renovation contract, structural inspectors discover concealed water damage that requires adding waterproof membrane work not included in the original scope. The contractor agrees to perform the added work at a negotiated price. How should the buyer formalize this change?
Select an answer to reveal the explanation.
Short Explanation
When a renovation uncovers hidden water damage, a quick email approval is an invitation for a payment dispute later. You protect both the budget and the timeline by putting agreed scope, cost, and schedule changes into a formal bilateral modification. The trap is skipping formal documentation or leaving price and schedule terms open just to keep crews moving.
Full Explanation
Because both parties are agreeing to add work outside the original contract baseline for a negotiated price, the buyer must Execute a written bilateral contract modification detailing the revised scope, price, and schedule. A bilateral modification establishes mutual assent, updates the legal baseline for inspection and invoicing, and ensures budget encumbrances match the new contract ceiling. Choosing to Issue an informal email approving the extra work and pay the difference on the final invoice bypasses signature authority, audit trails, and encumbrance controls. Trying to Instruct the contractor to absorb the added scope under the original lump-sum price is inequitable and unenforceable when concealed site conditions fall outside the original specifications. Issuing a decision to Execute a unilateral notice to proceed describing the added work and settle its price after completion leaves the county exposed to open-ended claims because price and schedule are not fixed before work begins. As an exam caveat, substantial scope additions must remain within the general scope of the original solicitation or else they risk functioning as an improper non-competitive award. Operationally, verify available project contingency funds, obtain required leadership or board approvals, and log the executed change order in the contract file before work begins.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.