Business-critical systems adjacent to 911 dispatch depend on unfinished hybrid network and DR designs. The migration board must choose what moves now versus later. Which selection best reflects timing judgment?
Select an answer to reveal the explanation.
Short Explanation
If 911-adjacent gear needs network and DR designs that aren’t done, it waits—period. Move safer candidates now. Schedule optics don’t outrank public-safety readiness.
Full Explanation
Selecting migration candidates includes timing: defer business-critical 911-adjacent systems until hybrid networking and DR meet RTO/RPO and stakeholder approval, while progressing lower-risk waves. Forcing weekend cutovers for optics, retiring critical systems due to complexity, or skipping DR for public safety are inappropriate.