Quiz 4 Question 17 of 20

Maintenance engineers at a refinery covered by OSHA Process Safety Management (29 CFR 1910.119) plan to replace a corroded carbon-steel valve in a covered highly hazardous chemical line with a valve of a different alloy and actuator type. Which requirement must be completed before putting the modified line into service?

Select an answer to reveal the explanation.