Quiz 3 Question 19 of 20

A chemical plant covered by OSHA Process Safety Management (29 CFR 1910.119) operates pressurized chlorine storage vessels and relief valves that have been in service for twelve years without documented thickness testing or relief-device inspections. Which PSM program element directly requires ongoing inspection, testing, and quality assurance of this critical process equipment?

Select an answer to reveal the explanation.

Motivation