Quiz 3 Question 16 of 20

A maintenance contractor needs to weld a pipe support bracket onto a structural beam directly above a covered process line containing flammable hydrocarbons at a facility regulated under OSHA Process Safety Management (29 CFR 1910.119). What must the facility require before any arc welding begins?