A team has spent the quarter converting a proof of concept into a governed release process for a transformed service. Which statement best summarises the release condition for it?
Select an answer to reveal the explanation.
Short Explanation
You don't ship a transformed service just because it generated, compiled, or wowed a demo. You need tests passed, review completed, and operational readiness met before it replaces or runs alongside the legacy service.
Full Explanation
The release condition is that the service must pass its tests, complete review, and meet operational readiness before it replaces or is exposed alongside the legacy service. The other milestones are real progress but stop short of proving the service is safe for production, which is what the three-part gate confirms.
The code-generation-completes-without-error condition is wrong because generation is a production step, not a correctness or safety check.
The compiles-and-starts condition is wrong because it confirms initialisation, not business correctness or recovery readiness.
The demo-well-received condition is wrong because audience reaction is not a governance criterion.
For the exam, state the release gate as tests, review, and operational readiness together.