During the Validate phase, how should performance of the generated Java module be compared to the original COBOL?
Select an answer to reveal the explanation.
Short Explanation
You don't guess performance here. Run the original COBOL and the generated Java under production-representative transaction volumes, then compare response times and resource consumption. That's how you prove the Java module meets the same SLAs.
Full Explanation
Meaningful validation requires running both COBOL and generated Java under production-representative transaction volumes, comparing response times and resource consumption to confirm SLA parity. Java being faster, Spring Boot startup under 10 seconds, or waiting for production OMEGAMON monitoring are insufficient because they don't provide a controlled baseline comparison.