The assembled sidewalk-heave pipe is checked with a smoke pass, functional transform and routing cases, a load, scale, and security pass, and deliberately defective frames to see whether integrity holds. Which system-test set is that?
Select an answer to reveal the explanation.
Short Explanation
Once the sidewalk-heave pipe is assembled, the system-test set is a smoke pass, functional transform and routing cases, load, scale, and security, plus deliberately defective frames to see whether integrity holds. That is smoke, functional, non-functional, and fault injection. Component-only, a Chapter 7 canary, and model-only miss that assembled-pipe set.
Full Explanation
The assembled pipe gets smoke, functional, non-functional, and fault-injection system tests. Component-only, Chapter 7 canary, and model-only miss that set.