A county risk register wants to import scanner base scores unchanged for every civic asset. What caution should guide severity mapping?
Select an answer to reveal the explanation.
Short Explanation
A medium on a forgotten printer is not the same medium on the payment portal. Take the scanner number, then weigh who can reach it and what it protects.
Full Explanation
When a county risk register wants to import scanner base scores unchanged for every civic asset, caution that base scores need asset criticality and exposure context before they become real priorities. Base scores do not already include every environmental factor for municipal systems. Blindly lowering all scores by two points for government networks is arbitrary and unsafe. Informational findings alone are not the only items that belong on a civic risk register. Exam caveat: environmental scoring or local policy overlays should be explicit and repeatable. Operational check: adjust prioritization using public exposure, data sensitivity, and service criticality; document the mapping rules; and review exceptions with the county risk office. Document the rationale in the municipal engagement notes so later civic responders know which boundary was honored and which failure modes the rejected options would create for public services. Document the rationale in the municipal engagement notes so later civic responders know which boundary was honored and which failure modes the rejected options would create for public services. Document the rationale in the municipal engagement notes so later civic responders know which boundary was honored and which failure modes the rejected options would create for public services.
Prefer to study offline? Printable PDF study book + test engine ($7.50, unofficial). These questions stay free here.